Saturday, April 22, 2017

The following summarizes the work efforts during the third week of the Miller Project.

1) New USGA spec sand was hauled to all additional greens and tilled in to existing profile to a depth of 8".  This will ensure a uniform profile in our putting greens root zone.

2) The greens complex on #13 was roughed in and work has begun on the new putting green area.  The scope of this work will now include complete reconstruction of the putting green, with new drainage, gravel and sand bed.  This will also include new irrigation.

3) Greenside bunkers were cleaned out on holes 1,2,6,7 and 8.  This includes all old sand and old drain pipes.

4) 2 rain days were experienced 4/18 and 4/19, but work efforts continued on these days in spite of the rain.

5) Scott Miller will be onsite 4/24-4/27 to inspect scope of work completed as well as approve subgrades to #4, #13 and new putting green. 

I will report more details as we progress through next week.

Regards,

Donny Latham