The following summarizes the work efforts during the
fourth week of the Miller Project:
(1) Finished hauling sand to all repaired greens and
rototilled into existing rootzone
(2) Fummigated all repaired greens as well as
approximately 4,000 SF of existing nursery green by maintenance facility
(3) Finished rough shaping of 4 and 13 greens and new PG
(4) Installed drainage and gravel blanket on 4 green
(5) Began excavation of irrigation heads
(6) Expanded 13 green shaping and bunkers as per
architects direction
(7) Began bunker work on 7 green
(8) Scott Miller's visit on Monday through Wednesday
approved subgrades on 4,13, and PG
(9) Began cutting sod on tees to be repaired
(10) Initial layout of irrigation heads on 4,13 and PG
Donny Latham