The following summarizes the work efforts during the fourth week of the Miller Project:

(1) Finished hauling sand to all repaired greens and rototilled into existing rootzone

(2) Fummigated all repaired greens as well as approximately 4,000 SF of existing nursery green by maintenance facility

(3) Finished rough shaping of 4 and 13 greens and new PG

(4) Installed drainage and gravel blanket on 4 green

(5) Began excavation of irrigation heads

(6) Expanded 13 green shaping and bunkers as per architects direction

(7) Began bunker work on 7 green

(8) Scott Miller's visit on Monday through Wednesday approved subgrades on 4,13, and PG

(9) Began cutting sod on tees to be repaired

(10) Initial layout of irrigation heads on 4,13 and PG
 